Solutions · Commercial & Industrial · Data Centres

Data Centres & AI Infrastructure

Battery storage for hyperscale and colocation operators. Bridge multi-year grid interconnection delays, replace diesel UPS, manage AI compute step loads. Utility BESS engineered for European data-centre integration.
What is a data-centre BESS
A data-centre BESS pairs lithium-iron-phosphate batteries with hyperscale and colocation sites. It bridges multi-year grid interconnection waits — industry-reported 3–7 years across major EU markets — replaces diesel UPS to satisfy CSRD and EU Taxonomy scope-1 disclosure, and absorbs AI training load spikes legacy UPS can’t track. Henley Power supplies the utility platform in 2 MWh and 5 MWh containerized blocks with grid-forming PCS as standard and IEC 61850-7-420 DER profile support. Chinese scale. Global service. Manufactured in Shandong, China. European projects serviced from Romania.

01 — THE DATA-CENTRE-PLUS-STORAGE CASE

Why hyperscalers and colocation operators add batteries

Data centre demand has decoupled from grid build-out timelines. AI compute, hyperscale expansion, and the migration off legacy UPS architecture converge on one point — the operator now needs storage to make the project bankable, not just resilient.

Grid interconnection delay is the dominant project blocker. Major TSOs across Frankfurt (Amprion / TenneT), Dublin (EirGrid), Amsterdam (TenneT NL), and London (National Grid ESO) face MV/HV connection queues of 3–7 years for new data centre loads above 50 MW, depending on zone and feeder capacity — figures aggregated across published TSO connection-queue disclosures and Ember’s June 2025 grid-for-data-centres analysis. The connection itself isn’t the issue — it’s the upstream substation and transmission build that gates the date. Battery storage at the site lets the operator go live on a constrained import contract, then scale as the grid catches up. The BESS bridges the gap between commissioning and full-grid availability without forcing the operator to commit diesel-UPS capex twice.

Diesel UPS replacement is regulatory pressure now, not just sustainability ambition. EU Taxonomy disclosure and CSRD reporting both require scope-1 emissions accounting for backup-generation diesel use. Major hyperscalers have signed climate-neutrality commitments tied to 2030. Lithium-iron-phosphate UPS replaces 30-second diesel start-up cycles with sub-second response, removes the on-site fuel inventory, and converts a scope-1 line item into a scope-2 grid draw covered by the operator’s PPA stack.

AI training spikes have overrun legacy UPS dynamic response. Modern GPU clusters ramp from idle to nameplate within seconds, then drop again as workloads complete. Traditional flywheel and battery-string UPS architectures were sized for an outage event, not repeated multi-MW load swings during normal operation. Grid-forming BESS at data-hall scale absorbs the swings without dragging on the grid feeder or triggering downstream voltage events that propagate into the dual-cord IT load.

02 — WHAT THE BATTERY DOES

Four duty cycles, one platform

Grid bridge

Battery sized to the gap between import-contract MW and full-load demand. Site goes commercially live earlier; the BESS recharges off-peak and discharges during peak compute. Closes a project schedule gap that capex alone can’t close.

Diesel UPS replacement

Lithium-iron-phosphate replaces flywheel and lead-acid UPS strings. Sub-second response, no fuel logistics, no scope-1 emissions accounting. Compatible with N+1 and 2N redundancy architectures common at hyperscale tier.

AI step-load buffering

Absorbs GPU-cluster step loads on the millisecond scale. Grid-forming PCS control prevents swings from propagating upstream into the feeder or downstream into the dual-cord IT load.

Demand response revenue

When sized beyond bridge requirement, the BESS qualifies for capacity markets and flexibility programmes. Secondary revenue layer that offsets capex over the operating life — stacks on top of the bridge use case without competing with it.

03 — INTEGRATION ARCHITECTURE

Three ways to wire it

Data centre BESS doesn’t fit a single architecture. The right configuration depends on whether the project is greenfield, retrofit, behind a UPS, or integrated at the campus level. The platform constants don’t change between modes: Tier-1 LFP cells from publicly listed manufacturers, multi-supplier homologated, and grid-forming PCS as standard across all utility BESS containers, with IEC 61850-7-420 DER profile support — project-specific edition confirmed at commissioning.

Mode A

Campus-level grid-attached

BESS containers tied to the data centre MV substation. Independent inverters, independent control. Easiest to retrofit on existing campuses, easiest to scale as the IT load grows. The default for new EU and UK colocation and hyperscale developments.

Default

Mode B

Behind-UPS integration

BESS sits between the utility feed and the existing UPS infrastructure. The legacy UPS keeps doing IT-load conditioning while the BESS handles grid-bridge and demand-response duty. Used when the operator wants the storage benefit without retiring existing UPS assets prematurely.

Mode C

Greenfield direct-to-IT-bus

BESS replaces the legacy UPS entirely, sized at the data hall level. Grid-forming PCS provides ride-through and step-load response that lead-acid plus diesel can’t match on combined performance. Used in greenfield builds where the operator is starting clean.

04 — SIZING LOGIC

How to size a data-centre BESS

Three levers drive the sizing study. Get them wrong and the BESS either oversized for capex or undersized for the operator’s RTO target.

Lever 01

Bridge MW gap

Difference between contracted import MW and design-point IT load. Sets the BESS power rating at minimum. PCS sized to peak gap, not nameplate IT.

Lever 02

Bridge duration

Hours the operator runs at the gap during peak compute windows. Typical 1–4 hours; sets the energy stack. Cooling load profile factors in here too.

Lever 03

AI step-load envelope

Ramp-rate and step-magnitude expected from AI workloads. Larger steps require denser PCS sizing relative to the energy stack — a 2-hour bridge with aggressive AI load isn’t the same engineering as a 2-hour bridge with steady webhost load.

Rule of thumb

20 MW data centre on a 10 MW import contract: typically a 10 MW / 20–40 MWh BESS for a 2–4 hour bridge duration. 100 MW hyperscale campus on phased interconnection: typically 30–60 MW / 60–180 MWh distributed across multiple containers. These are starting points for feasibility, not engineering numbers — actual sizing factors in the operator’s RTO/RPO targets, the AI compute mix, the cooling load profile, and the TSO interconnection schedule.

Got a data centre stuck in the interconnection queue? We'll size the bridge BESS — and release the SLD package after NDA — with you.

05 — RECOMMENDED HENLEY PLATFORM

Two containerized blocks

The utility BESS platform is application-agnostic at the container and PCS level. The same containerized blocks ship to data-centre, solar-plus-storage, wind-plus-storage, and standalone grid-scale projects. Phase 1 launch lineup is 2 MWh and 5 MWh — 3 MWh and 4 MWh are project-spec configurations engineered on the same platform, quoted on request. Selection between blocks comes down to the bridge MW gap, the duration target, and the campus footprint available on site.

UTILITY

HLY-BESS-Utility-2MWh

Utility-Scale BESS — 2 MWh Containerised.

2 MWh

2,232 kWh liquid-cooled LFP in a 20-ft ISO container — IPP solar farms, wind balancing, utility substations.

View product

UTILITY

HLY-BESS-Utility-3MWh · 4MWh · 5MWh

Utility-Scale BESS — 3 to 5 MWh Liquid-Cooled Container.

3–5 MWh

3,344 / 4,180 / 5,015 kWh liquid-cooled LFP in 20-ft ISO containers — grid-scale storage, frequency response, BESS-as-a-service.

View product

06 — REFERENCE PROJECTS

Honest about where we are

Note from engineering

Henley Power’s deployed portfolio to date is dominated by utility solar-plus-storage and PV-storage-diesel hybrids — Inner Mongolia, Ningxia, Hebei, Henan, Shandong provinces in China, plus a Sahel-region microgrid in Chad. Data-centre-specific commissioned reference projects are in development with European colocation operators.

The technical reality is that the BESS platform — 2 MWh and 5 MWh containerized blocks today, 3 MWh and 4 MWh as project-spec configurations — is application-agnostic at the container and PCS level. The engineering differences between utility solar pairing and data-centre integration live in the control logic, the protection coordination with the dual-cord IT load, and the SLA structure — not in the cell architecture or the cabinet. Pre-commissioning data-centre references and engineering studies are shared after NDA on request, and our deployed utility portfolio is the closest analogue at the platform level.

If your project needs a fully data-centre-deployed reference site as a pre-condition to specification, we’ll say so openly rather than over-promise. Browse current project portfolio →

07 — FAQ

Common questions

How is a BESS used as a grid-interconnection bridge?
When the import-contract MW lags the data centre’s design-point IT load, the BESS covers the gap. Site goes commercially live on the smaller contract, recharges during off-peak hours, and discharges during peak compute. Once the upstream grid build catches up, the BESS pivots to demand response and capacity-market participation. The bridge use case is where the value of an 18–36 month earlier go-live shows up directly on the operator’s revenue model.
Yes, when sized and protected correctly. Lithium-iron-phosphate response time meets the millisecond-scale switchover expectations standard for Uptime Institute Tier-III and Tier-IV facilities, where availability targets are 99.982% and 99.995% respectively. The trade-off is capex profile and protection coordination — BESS deployment usually involves recoordinating ground-fault and arc-flash schemes with the dual-cord IT load. Project-specific protection studies shared after NDA. Compatible with N+1 and 2N redundancy architectures.
Warranty insurance via licensed European insurer is available as a project option for DFI-financed and institutionally-backed tenders. Parent guarantee or escrow alternative on request.
AI workloads ramp from idle to nameplate within seconds and drop again as training jobs complete. Traditional flywheel and battery-string UPS architectures were designed for outage ride-through, not repeated multi-MW load swings during normal operation. Grid-forming BESS PCS at data-hall scale absorbs the swings on the millisecond level without propagating them upstream into the feeder. The control loop sees the IT step before the upstream feeder does.
For grid-bridge sizing, start with the gap between contracted import MW and design-point IT load, multiplied by the bridge duration target (typical 1–4 hours). For UPS-replacement sizing, start with the existing UPS capacity and adjust for the new step-load envelope from AI compute. Refine after running 12 months of plant load profile data and reviewing the TSO interconnection schedule. Detailed sizing studies released after NDA execution.

09 — RELATED SOLUTIONS

Adjacent applications

The same BESS platform deploys across data-centre, C&I, and grid-services use cases. Three closest siblings to data-centre BESS, in case the project mix calls for them.

SOLAR FARMS

SOLAR · CAPACITY FIRMING

Battery Storage for Solar Farms

Co-located battery storage for utility-scale solar PV plants — capacity firming, time-shift, and grid-export smoothing.

View solution

MICROGRID

MICROGRID · ISLAND OPERATION

Microgrid & Off-Grid Battery Storage

Islanded and grid-tied microgrids for islands, remote communities, military bases, and isolated industrial sites — full energy independence with renewable integration.

View solution

HYBRID

HYBRID · FUEL OFFSET

Hybrid Power Plant Battery Storage

Solar PV plus diesel or gas generators plus battery storage for off-grid mines, islands, and remote industrial loads — fuel savings 30–60%.

View solution